2020-11_6. (5) Clerks Report: Playground Inspection

The Original inspection report is in the councillors shared folder:

https://1drv.ms/b/s!AtoBPP1dQfR0g6Fs_KxrWt502vjPzQ?e=IDYUEH

There were some low risk items to consider. The Clerk / Village Operative have noted these recommendations and will monitor or take corrective action.

There was no risk assessment taken on the cable runway seat connection as it requires dismantling.

The inspector recommended impact testing the surface under the cable runway to ensure absorbing properties are maintained.

There were no medium or high risk items that require action.

  • Posted: 10th November 2020